Solicitation
W9123826BA012
Due
September 1, 2026, 9:00 AM PDT
Location
Sacramento, California
Source
SAM.gov
Official Tender Text Used
The SAM.gov notice states USACE Sacramento District is soliciting construction of a new Pumping Plant 5 facility in Sacramento, CA for the American River Common Features, Natomas Basin Project. The existing PP5 will be demolished and the new facility constructed about 300 feet up the West Drainage Canal to support Reach B levee improvements.
Scope Summary
USACE Sacramento District (SPK) requires construction of a new pumping plant facility (PP5) in Sacramento, CA as part of the American River Common Features, Natomas Basin Project. The existing Pumping Plant 5 will be demolished and a new facility constructed approximately 300 feet up the West Drainage Canal to allow completion of Reach B levee improvements. Work includes seepage berm, adjacent levee construction, and raising discharge pipes above the 200-year water surface elevation. Primary trades involved are heavy civil, structural, mechanical/pump installation, and earthwork/levee construction. No estimated construction value is stated in the notice; NAICS 237990 (Other Heavy and Civil Engineering Construction) applies.
Eligibility Requirements
- Full solicitation document must be reviewed for contractor eligibility — not fully stated in this notice
- NAICS 237990 — Other Heavy and Civil Engineering Construction — primary code applies
- USACE federal contractor registration required (SAM.gov active registration mandatory)
- Likely requires USACE or agency prequalification — confirm in full solicitation
- Performance and payment bonds likely required at 100% given federal heavy civil scope — confirm in solicitation
- Prevailing wage / Davis-Bacon Act likely applicable — federal USACE contract in California
- California contractor's license required (Class A General Engineering Contractor expected)
- No set-aside stated — open competition, but verify in full solicitation documents
Key Dates
Solicitation Published: 2026-08-13
Amendment 0001 and Amendment 0002 have already been issued — download latest documents from SAM.gov before doing any takeoff work
Solicitation Last Modified: 2026-08-18
Reflects Amendment 0002 posting — verify no further amendments before bid submission
Bid Response Due: 2026-09-01 at 09:00 AM PDT
Hard federal deadline. Late submissions typically rejected without exception. Approximately 14 calendar days from last amendment — very short window.
Red Flags
Extremely Tight Bid Window
Response due 2026-09-01, roughly 14 calendar days after the last amendment (2026-08-18). For a heavy civil pumping plant and levee project, this is an extremely compressed estimating window. Expect incomplete takeoff time and potential for scope gaps.
Two Amendments Already Issued
Amendments 0001 and 0002 were issued before the notice was widely reviewed. Scope, drawings, or requirements may have already changed. Bidding from original documents without downloading the latest amendments will likely result in a non-responsive bid.
Davis-Bacon Prevailing Wage Likely
This is a federal USACE construction contract in California. Davis-Bacon Act wages almost certainly apply. Certified payroll requirements will add administrative burden. Confirm wage determinations in full solicitation and factor compliance cost into bid.
Demolition of Existing Facility in Scope
Existing PP5 must be demolished before or during new construction. Hazmat (asbestos, lead paint) in the existing pump structure is not addressed in this notice. Full solicitation and site investigation reports must be reviewed before pricing demo.
Active Flood Control / Levee Site
Work is adjacent to the Sacramento River levee system in the Natomas Basin — a federally critical flood control area. USACE, CVFPB, and local agency permit windows, seasonal work restrictions, and restricted shutdown windows for drainage structures are highly probable. Verify in full specs.
100% Performance and Payment Bonds Expected
Federal construction contracts under 40 U.S.C. § 3131 (Miller Act) require 100% performance and payment bonds. This is a custom heavy civil facility — bonding capacity and surety relationship must be confirmed before bidding.
No Construction Value Stated
Estimated contract value is not disclosed in the notice. Cannot assess bid/no-bid fee ROI, bonding sufficiency, or subcontractor interest without knowing the magnitude. Pull the solicitation immediately to find any cost range or IGCE reference.
Discharge Pipe Above 200-Year WSE Requirement
Discharge pipes must be raised above the 200-year water surface elevation — a specific engineered requirement. Coordination with hydraulic design drawings is critical. Any misread of elevation benchmarks could cause costly rework or rejection of completed work.
Bid / No-Bid Read
This contract suits a heavy civil contractor with demonstrated experience in flood control, pump station construction, and federal USACE projects in California — ideally with an active USACE relationship and prior levee or water control work in the Sacramento District. The 14-day bid window after Amendment 0002 is punishingly short for a project of this complexity; contractors without plans already pulled and a sub network ready to respond should strongly consider a no-bid. The absence of a stated construction value and two pre-existing amendments are additional caution flags — pull the full solicitation immediately or walk away.